GEPCO · Rooftop solar

GEPCO net metering & net billing — apply, fees, timeline

Gujranwala Electric Power Company processes rooftop-solar net-metering applications within 8–12 weeks. Under SRO 251(I)/2026, new licences use the net-billing schedule — this page covers both regimes end-to-end.

Region served: Gujranwala, Sialkot, Gujrat, Hafizabad, Narowal & Mandi Bahauddin

Gujranwala Electric Power Company accepts net-metering applications from every premises with a sanctioned load ≥1 kW within its licence area. Rural feeders are eligible; the only exclusions are seasonal agricultural connections and unmetered street-lighting circuits.

How to apply for GEPCO net metering

  1. Engage an AEDB-certified vendor — non-certified installs are rejected at inspection.
  2. Complete the physical installation with an IEC 61683 / IEC 62109 certified inverter and grid-tie protection.
  3. Prepare documents: CNIC, latest $GEPCO bill, single-line diagram, vendor certificate, undertaking on Rs. 100 stamp paper.
  4. Submit online at https://www.gepco.com.pk/net-metering.
  5. Pay processing + meter fee (Rs. 5,000 (processing) + Rs. 30,000–45,000 (bi-directional meter)).
  6. GEPCO inspection team visits within 8–12 weeks, installs the bi-directional meter and energises the connection.
  7. Sign the 7-year Energy Purchase Agreement (net-billing schedule for post-March-2026 applications).

Costs & timelines for GEPCO (2026)

ItemAmount / timeline
Application processing feeRs. 5,000
Bi-directional meterRs. 30,000–50,000
3-phase upgrade (if needed for >5 kW)Rs. 60,000–120,000
End-to-end processing8–12 weeks
Contract duration7 years, renewable

Payback under the 2026 net-billing regime

Before SRO 251(I)/2026, $GEPCO net-metering customers received the full retail tariff (Rs. 22–27/unit) for every exported unit. Under net billing, export is credited at NEPRA's generation-cost benchmark (~Rs. 11–13/unit) while import is charged at full retail. For a 5 kW residential system exporting ~30% of generation, this pushes payback from 3–4 years to 4–5.5 years — still one of the best returns of any consumer investment in Pakistan.

Run your own numbers in the Solar Payback Calculator with the 2026 defaults pre-loaded.

Frequently asked questions